CPM Logic Relationships, Predecessor/Successor

The dependency links between activities in a critical path method schedule, defining which activities, predecessors, must happen before others, successors, can start or finish. These relationships are the actual logic that determines the [[concept-critical-path|critical path]], not just a list of dates.

Why it matters

Two activities that could genuinely overlap get treated as sequential purely because of how the logic relationship was set up, not because the real-world work actually requires it, and that single choice can stretch a schedule's calculated duration for no real reason.

On a real project

A scheduler links drywall installation to start only after all electrical rough-in is fully complete in every room, when the real-world sequence actually allows drywall to begin in rooms where rough-in is already done, a looser logic relationship that would shorten the schedule.

Who this matters most to

A Scheduler sets the logic relationships between activities, the actual decisions that determine which activities end up on the critical path.

Where this goes wrong

A scheduler links two activities with a simple finish-to-start relationship when the real-world logic actually allows them to overlap. That single choice artificially extends the schedule's calculated duration, making the project look further behind than the real site conditions actually require.